SFTS manage all aspects of 33 kV work on an 81 MW wind farm
SFTS are contracted to manage all aspects of the 11 kV network for several installations of national importance

SFTS are contracted to provide Senior Authorised Persons to a major renewables company for all of their sites.

SFTS were engaged at a very late stage in the commissioning phase of a 21 MW solar farm in northern Scotland which operated at 33 kV. SFTS were tasked with ensuring that the 33 kV network was fully commissioned and would meet strict DNO acceptance parameters.


SFTS successfully commissioned all of the client's 33 kV network, solving several engineering problems encountered in the short space of time between engagement and completion, to meet the strict deadline set for DNO connection and energisation!

After a destructive failure occurred on the 11 kV tertiary circuit of a 400 kV transformer at the onshore substation of a 450 MW offshore wind farm, SFTS were commissioned to lead the fault repair.

A 450 MW wind farm returned to optimal operating conditions due SFTS expertise and timely intervention!

SFTS were asked to test some 33 kV cables for a newly installed energy centre in West Central Scotland before first energisation.

Suite of testing on the cables including
Robust pre-energisation testing giving the client total confidence that their installation will stand up to the rigours of production.